To initiate preparations for installing the charger, we require additional information:
Installation Address: Provide the precise address where the charger is to be installed.
Architectural Project: Include a detailed architectural layout of the building and parking area. Highlight the planned location of the charging point and indicate the position of the main electrical panel.
Electrical Project: Furnish the electrical project of the building along with images of the main electrical panel.
Utility Contract: Submit a copy of the building's utility contract, encompassing grid tariff and consumption power agreement.
Charger Location: Specify whether you intend to mount the charger on a pole or a wall.
Cabling Preference: Indicate if cabling can be surface-mounted via installation pipes or if it should be concealed within walls or beneath pavement stones.
Cable Conduit: Detail the use of conduit or cable protection pipes connecting the charger installation point to the main electrical panel.
Power Cable: Select a power cable option, such as a 5G6 or equivalent 5-core cable with a 6mm² conductor cross-section.
CAT6 Communication: Incorporate a CAT6 cable connecting the main electrical panel to the charger for reliable communication between the LMC and the charger.
Internet Connection: Decide on either Wi-Fi or a network cable to link the LMC controller to the Internet.
Electrical Panel Space: Allocate room in the electrical panel for two 3-phase circuit breakers (6 standard DIN modules) and one 3-phase fault current protection (4 standard DIN modules).
In case you lack any essential information or possess only partial knowledge, we can facilitate an on-site inspection with one of our certified installers (NB: this option might not be available in your location yet, for more information please contact [email protected]).